A substation was being constructed by Siemens in Bicker Fen, Boston, for the new Triton Knoll Offshore windfarm located off the Lincolnshire coast.

With over 40 miles of underground cable from the Lincolnshire coast, the new substation will transform the generated electricity to a suitable voltage for the National grid. Once completed, Triton Knoll Offshore windfarm will be capable of providing clean and sustainable energy to over 800,000 UK homes.

Centrum Pile manufactured and supplied the piles for the various substation buildings and equipment that was to be built on the site. Across a 7 week installation period, Centrum pile supplied over 1500 No. 200mm and 250mm square precast concrete from lengths of 5m to 14m.